Construction Material Prices 2026: How Tariffs Are Changing Your Bids

Welder joining a steel beam on a construction site with the title Construction Material Prices 2026: How Tariffs Are Changing Your Bids and the Backus Estimating logo

Short answer: construction material prices in 2026 are rising faster than most bids. The producer price index for inputs to new nonresidential construction rose 13.3% between October 2025 and October 2026, the biggest jump in more than four years. Steel, copper, aluminum and diesel are leading the increase, mostly because of tariffs and fuel costs. If your estimates still use last year’s unit prices, your margin is probably already gone.

This guide explains what is driving prices, which trades are hit hardest, and how to price bids so a tariff change does not wipe out your profit halfway through a job.

Key takeaways

  • Input costs for nonresidential construction are up 13.3% year over year (October 2025 to October 2026).
  • Steel mill products are up 32.9%, copper and brass shapes 23.9%, aluminum 23.3% and diesel fuel 115.2%.
  • Lead times are getting longer for structural steel and mineral wool insulation, so schedule risk is now a cost risk too.
  • Bids that lock a price for 60 or 90 days without an escalation clause are the biggest danger for contractors right now.
  • A current, line-by-line material takeoff is the fastest way to see exactly how much of a bid is exposed to tariff-hit materials.

How much have construction material prices gone up in 2026?

According to the Associated General Contractors of America’s November 2026 analysis of federal producer price data, the cost of inputs for new nonresidential construction climbed 13.3% in the 12 months to October 2026. That is the largest annual increase in more than four years. Here is how the main materials moved over the same period:

Material or input Change, Oct 2025 to Oct 2026 Trades most affected
Diesel fuel +115.2% Sitework, earthwork, paving, hauling
Steel mill products +32.9% Structural steel, rebar, metal decking, misc. metals
Truck freight transportation +24.6% Every trade (delivery costs)
Copper and brass mill shapes +23.9% Electrical, plumbing, HVAC
Aluminum mill shapes +23.3% Storefronts, curtain wall, windows, ductwork
Liquid asphalt +11.5% Paving, roofing
Precast concrete products +9.9% Precast, site utilities

Not every material is climbing at the same rate. Softwood lumber has been far calmer than metals, which is why a single “add 10% for inflation” line on a bid is no longer good enough. The percentage that matters is the one for the materials in your scope.

Why are construction costs rising so fast?

1. Tariffs on metals and imported products

Tariffs of up to 50% on steel and aluminum, introduced in 2025, are still in place for most products contractors buy. A February 2026 Supreme Court ruling struck down some tariffs, but it did not change the rates on the large majority of construction materials. Domestic mills raise their prices when imported steel gets more expensive, so even “made in USA” material costs more.

2. Fuel and freight

Diesel more than doubled in a year. Diesel runs excavators, loaders, cranes and the trucks that deliver every load of material to site. Freight alone is up almost 25%, so delivery charges on quotes are worth checking line by line.

3. Longer lead times

Structural steel and mineral wool insulation are taking longer to arrive. When material shows up late, crews wait, schedules slip and general conditions grow. On a tight job, a six-week delay on steel can cost more than the price increase on the steel itself.

4. Bid prices are not keeping up

AGC’s 2026 outlook survey found that 53% of contractors list materials costs as a top concern, and about 40% have raised bid prices because of tariffs. Owners, however, are pushing back on higher numbers, so many contractors are absorbing the difference. That is a margin problem, not a pricing strategy.

Which trades are hit the hardest?

  • Steel and metals: structural steel, rebar, metal decking and miscellaneous metals carry the largest share of tariff exposure.
  • Electrical and MEP: copper wire, conduit fittings, busway and switchgear move with copper prices. Our electrical estimating and MEP estimating teams now update copper-sensitive line items for every bid.
  • HVAC: ductwork, coils and equipment use steel, aluminum and copper. See our HVAC estimating services.
  • Sitework and paving: diesel and liquid asphalt hit sitework and asphalt paving bids through equipment hours and material.
  • Glazing and openings: aluminum framing for storefronts and curtain wall is up more than 20%.

How should contractors price bids during tariff uncertainty?

Price from a fresh takeoff, not last year’s job

Copying quantities and unit costs from a similar past project is the quickest way to underbid in 2026. Start with an accurate quantity takeoff, then apply current supplier pricing to each line. You will see exactly which items carry tariff risk.

Shorten how long your price is valid

If your proposals say “valid for 90 days”, cut it to 30 days for metal-heavy and copper-heavy scopes. Ask suppliers how long their quotes hold and match your bid to the shortest one.

Add an escalation clause

A material price escalation clause ties part of the contract price to a published index or to supplier invoices. It protects both sides: the owner pays the real cost, and you are not forced to absorb a tariff that did not exist on bid day. Spell out the index, the base date, the trigger percentage and how the adjustment is documented.

Separate allowances for volatile items

For items like switchgear, structural steel and rooftop units, carry a clearly labeled allowance or unit-price line instead of burying the risk in a lump sum. It makes the bid easier to compare and easier to adjust.

Buy early when you can

Early purchase of long-lead items locks pricing and protects the schedule. Make sure you have storage, insurance and a payment schedule that covers stored materials before you commit.

Use value engineering on the biggest cost drivers

Swapping a material, changing a connection detail or adjusting a system can recover a large part of a tariff increase. Our value engineering services focus on the line items that moved most since design.

Track change orders closely

When a price jump happens mid-project, a well-documented change order is the only way to recover it. Keep supplier quotes, dates and index data together. If you need help pricing one, see our change order estimating.

What does this mean for owners and developers?

Owners should expect higher bids and fewer contractors willing to hold a fixed price for long. Budgets set early in design are likely out of date. A preconstruction estimate or an updated budget estimate at each design milestone keeps the project funded and avoids a painful surprise at bid opening.

How Backus Estimating helps you bid with current pricing

Backus Estimating prepares bid-ready estimates and takeoffs for contractors, subcontractors, developers and owners across all 50 states. Every estimate uses current material and labor pricing for your project’s location, with the tariff-sensitive items clearly marked so you know where your risk is. Send your plans through our free quote form, check our pricing, or see how it works.

Frequently asked questions

Are construction material prices going down in 2026?

No. As of late 2026, input prices for nonresidential construction are up 13.3% year over year, and metals and fuel are still climbing. Some materials, such as softwood lumber, are steadier, but there is no broad price drop.

How much have steel prices increased for construction?

Steel mill product prices rose 32.9% from October 2025 to October 2026. Structural steel, rebar and metal decking bids are the most affected.

How do tariffs affect construction bids?

Tariffs raise the cost of imported steel, aluminum and copper, and domestic suppliers usually follow those prices up. Bids priced before a tariff change can lose their entire margin if the contract has no escalation clause.

What is a material price escalation clause?

It is a contract term that adjusts the price when specific material costs rise or fall beyond an agreed percentage, measured against a named index or supplier invoices from a base date.

How often should I update unit prices in my estimates?

For metal-heavy, copper-heavy and fuel-heavy scopes, update prices for every bid and recheck before signing the contract. Monthly updates are the minimum for other trades in the current market.

In this article

Need an estimate?

Send your plans and get a free quote.

Upload your plans

Related articles

Turn this into a real number

Send your plans for a free, fixed quote.

Scroll to Top